The Australian Securities & Investments Commission (ASIC) is taking legal action against Australia’s largest market operator, ASX Limited, for allegedly making misleading statements related to its Clearing House Electronic Subregister System (CHESS) replacement project.
According to the regulator, statements made in ASX announcements on 10th February 2022 that the project remained “on-track for go-live” in April 2023 and was “progressing well” were misleading.
ASIC alleges these statements implied the project was meeting targets outlined in its project plan and was on track to meet future milestones, including to go live in April 2023. ASIC claims that at the time of the announcements, the project was not tracking to plan and ASX did not have any reasonable basis to imply the project was on track to meet future milestones.
ASIC Chair Joe Longo said, “ASX’s statements go to the heart of trust in the integrity of our markets. We believe this was a collective failure by the ASX Board and senior executives at the time.
“Companies and market participants rely on what the ASX says about its operations to make their own decisions and investments. We expect the ASX to be a place to list and invest with confidence. When the ASX falls short, it has wide ranging consequences across the market.
Longo said ASX’s CHESS replacement is a technology project of fundamental significance, replacing critical national infrastructure crucial to the operation of the Australian economy.
“Its critical importance was all the more reason ASX needed to ensure it told the Australian public the truth about how the project was tracking and whether it would be completed on time. We allege that the true state of affairs as at 10 February 2022 was that the project was not ‘progressing well’, contrary to ASX’s announcement.”
“The delay and subsequent pause of the project in November 2022 caused significant cost to ASX and market participants who relied on assurances as to the progress of the project and scheduled go-live date. The CHESS replacement project must be managed effectively and transparently. Failure to do so can lead to a lack of confidence in Australia as a market to attract investment.”
ASIC is yet to determine the penalty it will seek.